Despite the daily 100-degree temperatures, construction on our new rehabilitation center is progressing.  The concrete foundation was poured on August 29 followed by the daunting task of keeping the concrete wet for three days during the hot part of the day so that the concrete would cure properly.  The next step will be erecting the metal building, beginning in about a week.

Thank you for your hard work to Jack Ward Septic and Backhoe, Lovelace Well and Drilling Service, Silvio’s Plumbing, Silva Construction, and Whitley Steel Building Supply.